HOME
Blog
PUBLIC RELATIONS:
Time & Place
Tour of Locations
Photos (Port 8080)
Web Cam
Bibliography
Mailing List
OPERATIONS:
Public Timetable
Employee Timetable
Book of Rules
Makeup of Trains
Arranged Freight Service
Other Trains
CT1000
Interchange Points
OFFICE OF THE CHIEF ENGINEER:
Givens & Druthers
Standards
Materials
Layout Design
Construction Milestones
Equipment Roster (Port 8080)
Work Orders
HUMAN RESOURCES:
Employment Opportunities
Roster of Enginemen
MAPS:
System Map
Philadelphia Division
Middle Division
Pittsburgh Division
PROCUREMENT:
RFP's
Purchase Orders
INVESTOR RELATIONS:
Stockholders
MISC.:
Diner Needs
Harrisburg Industries
Prototype References
Ops Primer
YORK HAVEN SHOPS:
Introduction
Heavyweight Sleepers - paint, letter 15 cars
EMD F3 Phase II - kitbash, paint, letter 11 locomotives
B60b Baggage Cars - build, paint, letter 28 cars
P70k, P70gs, PLC70 - kitbash, paint, letter 9 cars
BM70k Baggage/Mail Cars - build, paint, letter 3 cars
"HARRISBURG" - kitbash, paint, letter business car
|
|
Work Orders
| Rough Construction Schedule |
| PROJECTED COMPLETION | SECTION |
| November 30, 2007 | BF interlocking. |
| December 31, 2007 | SF interlocking. |
| January 31, 2008 | MO interlocking. |
| February 28, 2008 | UN interlocking. |
| April 30, 2008 | Main line between Cassandra and MO. Prerequisites: Install custom crossovers at ROCKVILLE; Power frogs of DAY interlocking; Construct Level III framing at Cresson. |
| TBD | Golden Spike Ceremony |
| May 15-18, 2008 | Open House: PRRT&HS Annual Meeting in Camp Hill. |
| | AR interlocking. |
| | Fascia on Level II Between West End of Harrisburg Station and BANKS. |
| | Cresson Wye and Yard. |
| | Irvona Branch/Cresson Secondary Loop. |
| | Cresson Secondary/New Portage Secondary Loop. |
| April 29-May 2, 2010 | Open House: PRRT&HS Annual Meeting in Camp Hill. |
| | Level III Scenery and Fascia. |
| | Upper Level Lighting (track lighting via ceiling). |
| | Level IIb Scenery and Remaining Fascia. |
| | Cumberland Valley Branch / LEMO. |
| | Harrisburg East Switching Area (MP 103.5 - 103.7)
- Harrisburg Storage Co. (implied)
- Kinney Shoe Co.
- Kingan Provision Co. (implied)
- J. I. Case Co. (implied)
- Harrisburg Freight Station and Keystone Warehouse Co. No. 1
- Railway Express Agency
- Harrisburg Gas Co.
|
| | Harrisburg Passenger Station Trackage. |
| | Level IIa Scenery and Remaining Fascia. |
| | Cresson Locomotive Facility Trackage. |
| Maintenance Tasks |
| LOCATION (East to West) | PENDING WORK |
| Miscellaneous: |
- Reprogram board ID of BDL168 #__ at Helix I.
- Provide power to booster for Level III.
- Provide PS15 power to BDL168 #18.
- Program board ID of BDL168 #18 and program into JMRI.
- Install lighting for Level II within benchwork of Level III.
- Paint Remaining Lower Level Benchwork.
- Lower Level Curtains?
- Yard Video Surveillance System at staging break points and reverse loop.
- Audio eBroadcast of Op Sessions - Shoutcast is one solution.
|
| DREW Staging / DREW: |
- Turnouts do not seem to provide NMRA clearance through the frogs. Atlas has been contacted. This issue only applies to first 30 or so turnouts purchased.
- Install 6 Tortoise switch machines, 3 NCE Switch-It's, and frog power in yard ladder.
- Power frogs.
- Realign detection breaks (Jeff Warner request)
- Labels on staging tracks to ID track numbers (dispatcher request - for crew)
|
| Helix One: |
- Replace reverse loop controller for reverse loop around base (damaged in flooding).
- Consider relocating two BDL boards to inside helix, remounted per other BDL's.
|
| Harrisburg: |
- Install Tortoise switch machines, NCE Switch-It's, and frog power on main line.
- Install uncoupling magnets in yard east of station.
- Create "approach" blocks (Jeff Warner request)
|
| Market Street (Harrisburg) Switching Area (MP 104.0 & MP 104.2): |
- Install Tortoise switch machines and frog power.
- Construct local control panel.
- Install fascia and car card boxes, then paint.
|
| Seventh Street (Harrisburg) Switching Area (MP 104.0 & MP 104.2): |
- Install Tortoise switch machines and frog power.
- Construct local control panel.
- Install fascia and car card boxes, then paint.
- Extend track to Montgomery & Co. (once HARRIS yard throat has been completed).
|
| Lucknow Switching Area: |
- Power frogs.
- Construct local control panel.
- Install fascia and car card boxes, then paint.
|
| ROCKVILLE: |
- Install custom crossovers at ROCKVILLE interlocking for Northumberland serial staging.
|
| DAY: |
|
| Helix Two: |
- Install and paint fascia.
|
| MG: |
- Install 12 Tortoise switch machines, 3 NCE Switch-It's, and power to frogs.
|
| BC: |
- Power track four (ran out of BDL contacts).
- Install SwitchIt decoder.
|
| Helix Three: |
- Helix Three may have settled in one corner, causing more grade in back corner; check and possibly add shims.
- Install and paint fascia.
|
| ASH Staging / ASH: |
- Install 7 Tortoise switch machines, 3 NCE Switch-It's, and frog power in yard ladder.
- Install 10 Tortoise switch machines, 3 NCE Switch-It's, and frog power in interlocking plant.
- Power frogs.
- Labels on staging tracks to ID track numbers (dispatcher request - for crew)
- Turnout to track 3 at ASH has tight guide rails and catches many locos; check gauge.
|
|
|